一)、储藏室~五层
C20 HRB335 as=30㎜ 根据前面计算结果取设计值计算:
1.L01: b×h=150×250
梁自重:1.2×25×0.15×0.25+20×0.02×[0.15+2×(0.25-0.1)]
=1.31KN/m
墙体重:1.2×22×0.12×(2.8-0.25)=8.08KN/m
梯板传:(1.2×4.2+1.4×2.0)×1.4×1/2=5.49 KN/m井道传:(1.2×4.2+1.4×2.0)×0.42/2=1.65 KN/m
q =16.53 KN/m
Mmax=1/8ql2=1/8×16.53×2.62=13.97KN·M
αs=M/fcmbh02=13.97×106/(9.6×150×2102)=0.22γs=(1+(1-2αs )1/2 )/2=0.874
As=M/γsfyho=13.97 ×106/ (0.874×300×210) =253.66㎜2 选用2φ14 ㎜2
2.L02: b×h=150×130
为暗梁,根据构造配筋
As=308
3.L03: b×h=150×130
为暗梁,根据构造配筋
4.L04: b×h=240×300
梁自重:1.2×25×0.24×0.3+20×0.02×[0.24+2×(0.3-0.1)]=2.42KN/m楼板传:(1.2×4.2+1.4×2.0)×(3.5+3.9)×1/4=14.50KN/m
q =16.92KN/m
Mmax=1/8ql2=1/8×16.92×2.62=14.30KN·M
αs=M/fcmbh02=14.30×106/(9.6×240×2602)=0.092γs=(1+(1-2αs )1/2 )/2=0.952
As=M/γsfyho=14.30 ×106/ (0.952×300×260) =192.58㎜2选用2φ14 As=308㎜2
5.L05: b×h=240×300
梁自重:1.2×25×0.24×0.3+20×0.02×[0.24+2×(0.3-0.1)]=2.42KN/m墙自重:1.2×(22×0.12×2.5×1.2-0.9×2.1×0.5)÷1.2=6.98 (左侧有)楼板传:q1=(1.2×4.2+1.4×2.0)×3.6×1/4=7.06KN/m
q2左=(1.2×4.2+1.4×2.0)×1.5×1/2=5.88KN/mq2右=(1.2×4.2+1.4×2.0)×2.4×1/4=4.70KN/m
q左 =22.34KN/m q右=14.18 KN/m
L01传集中力:L01自重:1.31KN/m
L01上墙自重:1.2×22×0.12×2.55=8.08
楼板传L01:(1.2×4.2+1.4×2.0)×1.5×//4=2.94 KN/m
p =(1.31+8.08+2.94)×1.5×1/2= 9.25KN
RA=[1/2×14.18×2.42+9.25×2.4+22.34×1.2×(0.6+2.4)]/3.6=39.85KN RB=1.2×22.34+9.25+14.18×2.4-RA =30.24KN
当V=0或最小时M最大,令V=0处距B支座x,则30.24-14.18x =0,得x=2.13Mmax=30.24×2.13-1/2×14.18×2.132=32.24 KN·M
αs=M/fcmbh02=32240000/(9.6×240×2602)= 0.207 γs=(1+(1-2αs )1/2)/2=0.883
As=M/γsfyho=32240000/0.883×300×260=468 选用3φ18 As=763㎜2
6.L06: b×h=240×300
梁自重:1.2×25×0.24×0.3+20×0.02×[0.24+2×(0.3-0.1)]=2.42KN/m楼板传:q1=(1.2×4.7+1.4×2.0)×2.1×1/4=4.43KN/m
q2左=(1.2×4.7+1.4×2.0)×5.1×1/4=10.76KN/mq2右=(1.2×4.2+1.4×2.0)×3.6×1/4=7.06KN/m
q左 =17.61KN/m q右=13.91 KN/m
L04传集中力:L04自重:2.42KN/m
楼板传L04:(1.2×4.2+1.4×2.0)×2.9×1/4+(1.2×4.7+1.4×2.0)×4.2×1/4=14.55 KN/m
p =(2.42+14.55)×2.9×1/2=24.61KN
RA=[1/2×13.91×0.722+24.61×0.72+17.61×0.6×(0.3+0.72)]/1.32=24.32KN RB=0.6×17.61+24.61+13.91×0.72-RA =20.87KN当V=0或最小时M最大,令V=0处距A支座x,
则24.32-17.61×0.6-24.61-13.91(x-0.6)=0,得x<0,则V最小处为x=0.6,此时Mmax= 24.32×0.6-17.61×0.6×0.6×1/2=11.42 KN·M
αs=M/fcmbh02=11420000/(9.6×240×2602)= 0.073 γs=(1+(1-2αs )1/2)/2=0.962
As=M/γsfyho=11420000/0.962×300×260=152.19 选用2φ16 As=402㎜2
7.LL01: b×h=240×300
梁自重:1.2×25×0.24×0.3+20×0.02×[0.24+2×(0.3-0.1)]=2.42KN/m楼板传:(1.2×3.5+1.4×2.0)×1.5×1/2=5.25KN/m
q =7.67KN/m
Mmax=1/11ql2=1/11×7.67×3.92=10.61KN·M
αs=M/fcmbh02=10.61×106/(9.6×240×2602)=0.068γs=(1+(1-2αs )1/2 )/2=0.965
As=M/γsfyho=10.61×106/ (0.965×300×260) =140.96㎜2 选用2φ14 As=308㎜2
8.XL01: b×h=240×300
梁自重:1.2×25×0.24×0.3+20×0.02×[0.24+2×(0.3-0.1)]=2.42KN/m
LL01传来集中力:p=1/2×7.67×3.9=14.96KN
Mmax=1/2ql2+pl=1/2×2.42×1.52+14.96×1.5=25.16KN·Mαs=M/fcmbh02=25160000/(9.6×240×2602)= 0.162
γs=(1+(1-2αs )1/2 )/2=0.911
As=M/γsfyho=25160000/0.911×300×260=353 选用3φ18 As=763㎜2
二)、六层
C20 HRB335 as=30㎜
1.L01: b×h=150×250
梁自重:1.2×25×0.15×0.25+20×0.02×[0.15+2×(0.25-0.1)]=1.31KN/m楼板传:(1.2×4.85+1.4×2.0)×2.9×1/4=6.25KN/mL06传集中力p1:
L06自重:2.42KN/m
楼板传L06:q1=(1.2×4.2+1.4×2.0)×0.9×1/2=3.53KN/m
q2左=3.53KN/m
q2右=(1.2×4.2+1.4×2.0)×0.86×1/2+3.53=6.9KN/m
p1 =[1/2×6.9×1.52+3.53×0.9×(0.9/2+1.5)]/2.4=5.82KNp2=6.9×1.5+3.53×0.9-5.82=7.71 KNq=1.31+6.25=7.56 KN/m p1 =5.82KN
RA=[1/2×7.56×2.92+5.82×2.0)]/2.9=14.98KN RB=7.56×2.9+5.82-RA =12.76KN
当V=0或最小时M最大,令V=0处距B支座x,则7.56x=12.76,得x=1.69,此时
Mmax= 12.76×1.69-7.56×1/2×1.692=10.77 KN·M
αs=M/fcmbh02=10770000/(9.6×150×2102)= 0.170 γs=(1+(1-2αs )1/2)/2=0.906
As=M/γsfyho=10770000/0.906×300×210=188.59 选用3φ14 As=461㎜2
2.L02: b×h=200×300
梁自重:1.2×25×0.20×0.30+20×0.02×[0.20+2×(0.30-0.1)]=2.04KN/m楼板传:(1.2×4.7+1.4×2.0)×(2.9/4+1.2/2)=11.18KN/m由前知,L06传集中力p2=6.9×1.5+3.53×0.9-5.82=7.71 KN
q=2.04+11.18=13.22 KN/m p1 =7.71KN
RA=[1/2×13.22×2.92+7.71×2.0)]/2.9=24.49KN RB=13.22×2.9+7.71-RA =21.56KN
当V=0或最小时M最大,令V=0处距B支座x,则13.22x=21.56,得x=1.63,此时
Mmax= 21.56×1.63-13.22×1/2×1.632=17.58 KN·M
αs=M/fcmbh02=17580000/(9.6×200×2602)= 0.135 γs=(1+(1-2αs )1/2)/2=0.927
As=M/γsfyho=17580000/0.927×300×210=243.08 选用4φ16 As=804㎜2
3.L03: b×h=150×300
梁自重:1.2×25×0.15×0.3+20×0.02×[0.15+2×(0.3-0.1)]=1.57KN/m楼板传:(1.2×4.85+1.4×2.0)×3.5×1/4=7.54KN/mL06传集中力p1:
L06自重:2.42KN/m
楼板传L06:q1=(1.2×4.2+1.4×2.0)×0.9×1/2=3.53KN/m
q2左=3.53KN/m
q2右=(1.2×4.2+1.4×2.0)×1.46×1/2+3.53=9.25KN/m
p1 =[1/2×9.25×1.082+3.53×0.9×(0.9/2+1..08)]/1.98=5.18KNp2=9.25×1.08+3.53×0.9-5.18=7.99 KNq=1.57+7.54=9.11 KN/m p1 =5.18KN
RA=[1/2×9.11×2.92+5.18×2.6)]/3.5=14.79KN RB=9.11×3.5+5.18-RA =22.28KN
当V=0或最小时M最大,令V=0处距B支座x,则9.11x=22.28,得x=2.45,此时
Mmax= 22.28×2.45-9.11×1/2×2.452=27.24 KN·M
αs=M/fcmbh02=27240000/(9.6×150×2602)= 0.280 γs=(1+(1-2αs )1/2)/2=0.832
As=M/γsfyho=27240000/0.832×300×260=419.86 选用3φ18 As=763㎜2
4.L04: b×h=200×300
梁自重:1.2×25×0.20×0.30+20×0.02×[0.20+2×(0.30-0.1)]=2.04KN/m楼板传:(1.2×4.7+1.4×2.0)×(2.6/4+1.62/2)=12.32KN/m由前知,L06传集中力p2=7.99 KN
q=2.04+12.32=14.36 KN/m p2 =7.99KN
RA=[1/2×14.36×3.52+7.99×2.6)]/3.5=31.07KN RB=14.36×3.5+7.99-RA =27.18KN
当V=0或最小时M最大,令V=0处距A支座x,则14.36x=27.18,得x=1.89,此时
Mmax= 27.18×1.89-14.36×1/2×1.892=25.72 KN·M
αs=M/fcmbh02=25720000/(9.6×200×2602)= 0.198 γs=(1+(1-2αs )/2=0.888
As=M/γsfyho=25720000/0.888×300×260=371.13 选用4φ18 As=1017㎜2
5.L05: b×h=240×300
同前1~5层。
6.L06: b×h=240×300
)1/2由前知,L06上荷载
q2左=3.53KN/mq2右=9.25KN/m
RA=[3.53×0.9×(0.9/2+1.08)+1/2×9.25×1.082)]/1.98=5.18KN RB=3.53×0.9+9.25×1.08-RA =7.99KN
当V=0或最小时M最大,令V=0处距A支座x,则9.25x=7.99,得x=0.86,此时
Mmax= 7.99×0.86-9.25×1/2×0.862=3.45 KN·M
αs=M/fcmbh02=3450000/(9.6×200×2602)= 0.027 γs=(1+(1-2αs )/2=0.987
As=M/γsfyho=3450000/0.987×300×260=44.83 选用3φ16 As=603㎜2
)1/2
7.L07: b×h=240×300
按简支梁承受均布荷载计算
梁自重:1.2×25×0.24×0.3+20×0.02×[0.24+2×(0.3-0.1)]=2.42KN/m楼板传:(1.2×4.7+1.4×2.0)×6.3×1/4+(1.2×4.2+1.4×2.0)×2.1×1/4=17.41KN/m
q =19.83KN/m
Mmax=1/8ql2=1/8×19.83×1.322=4.32KN·M
αs=M/fcmbh02=4.32×106/(9.6×240×2602)=0.028γs=(1+(1-2αs )1/2 )/2=0.986
As=M/γsfyho=3.79 ×106/ (0.988×300×260) =56.17㎜2 选用2φ14 As=308㎜
2
8.L08: b×h=150×250
按简支梁承受均布荷载计算
梁自重:1.2×25×0.15×0.25+20×0.02×[0.15+2×(0.25-0.1)]=1.31KN/m墙体重:1.2×22×0.12×(2.8-0.25)=8.08KN/m
楼板传:(1.2×4.2+1.4×2.0)×2.1×1/4+(1.2×4.85+1.4×2.0)×2.1×1//4=8.64 KN/m
q =18.03 KN/m
Mmax=1/8ql2=1/8×18.03×2.12=9.94KN·M
αs=M/fcmbh02=9.94×106/(9.6×150×2102)=0.157γs=(1+(1-2αs )1/2 )/2=0.914
As=M/γsfyho=9.94 ×106/ (0.914×300×210) =172.55㎜2 选用2φ14 As=308㎜2
9.LL01: b×h=240×300
梁自重:1.2×25×0.24×0.3+20×0.02×[0.24+2×(0.3-0.1)]=2.42KN/m楼板传:(1.2×3.5+1.4×2.0)×1.5×1/2+(1.2×4.7+1.4×2.0)×4.2/4=14.11KN/m
梁上墙体重:1.2×(5.24×4.2×2.4-2.9×1.3×0.5)÷4.2=14.55 KN/m
q =31.08KN/m
梁上集中力:p=1.2×25×0.24×0.24×2.4=4.15KN
Mmax=1/11ql2+pl=1/11×31.08×4.22+4.15×0.7=52.75KN·Mαs=M/fcmbh02=52.75×106/(9.6×240×2602)=0.339γs=(1+(1-2αs )1/2 )/2=0.784
As=M/γsfyho=52.75×106/ (0.7845×300×260) =862.57㎜2 选用4φ20 As=1256㎜2
10.LL02: b×h=240×300
同前1~5层LL01.
11.XL01: b×h=240×300
同前1~5层XL01.